Koh Lanta's long-discussed mainland bridge is set to start construction. The Department of Rural Roads plans to issue the order to begin work on Saturday, 14 November 2026. The 1.78 billion baht bridge will be 2.24 km long and take about three years to build, with opening planned for 2029. It will cut the sea crossing to about 2 minutes and reduce reliance on the vehicle ferry. Until then, nothing changes for anyone driving to the island.
The project at a glance
| Item | Detail |
|---|---|
| Cost | 1.78 billion baht |
| Link | Koh Lanta (Krabi) to the mainland |
| Length | 2.24 km |
| Design | Two-lane, cable-stayed, main span of up to 200 m |
| Build time | About 3 years |
| Planned opening | 2029 |
| Planned start | Saturday, 14 Nov 2026 |
The bridge should cut the sea crossing to about 2 minutes. It should also reduce reliance on the vehicle ferry.
Contracts and funding
Contracts for this bridge and the Songkhla Lake bridge were signed on 31 August 2026. Prime Minister Anutin Charnvirakul witnessed the signing. Department Director-General Phichit Hunsiri signed with the CMC Joint Venture and Malaysia's CHEC Construction (M) Sdn Bhd.
On 7 July 2026, the Cabinet approved a World Bank loan of 4.55 billion baht and a grant of 129.30 million baht for the two bridges.
How you get to Koh Lanta now
Drivers take a vehicle ferry to Koh Lanta Noi, then cross the Siri Lanta Bridge to Koh Lanta Yai. The Nation reported ferry waits of 2 to 3 hours at peak times.
Until 2029, everyone driving to the island still depends on the ferry.
What officials say
Deputy Transport Minister Sanpetch Boonyamanee said the bridge would make travel, tourism and freight safer and more convenient. He also said it would improve access to medical care and emergency help. He gave the 14 November start date while presenting the ministry's southern investment plans.
The companion project: Songkhla Lake bridge
The Songkhla Lake bridge is worth about 4.6 billion baht and is about 7 km long. It runs between Krasae Sin district (Songkhla) and Khao Chaison district (Phatthalung). It cuts the trip from almost 2 hours to 15 to 30 minutes. Sanpetch said it follows the same schedule as the Lanta bridge.
A decade in the making
In 2016, months after the Siri Lanta Bridge opened between Lanta Noi and Lanta Yai, the Krabi governor said a new mainland bridge was approved. That earlier plan was a 1.5 km bridge costing about 800 million baht, due by 2023. It was not built, so the road link has been planned for about a decade.
The new scope is larger, at 2.24 km and 1.78 billion baht, and the opening has slipped to 2029.
What it means for visitors
- Before 2029: Nothing changes. Ferry crossings continue, and peak-time waits can reach 2 to 3 hours.
- From 2029: A crossing of roughly 2 minutes should make access to the island, including medical and emergency access, much easier.
- Treat the dates as plans: The 14 November start is a plan, so a slip is possible. The 2016 plan missed its 2023 target.