Suvarnabhumi Airport, Bangkok's main international gateway, could double its annual passenger capacity to 120 million within about 7 years under Airports of Thailand's (AOT) fifth development plan. The plan adds a southern terminal and a fourth runway, and sits alongside an East Expansion project, a duty-free rework, new VIP and fast-track services, and a bigger budget for Don Mueang. The plans still need cabinet approval.
Suvarnabhumi capacity plan
Current capacity in fiscal 2026 is about 60 million passengers a year: 45 million at the main terminal and 15 million at SAT-1. AOT's fifth development plan could double that to 120 million within about 7 years.
The plan includes a southern terminal and a fourth runway, both expected to finish in 6 to 7 years. AOT will soon submit the plan to the cabinet, together with the East Expansion project.
East Expansion project
The terms of reference are ready, and procurement starts next year (2027). Construction is expected to take 4 years.
The project adds check-in counters, baggage conveyor belts and other service areas for at least 10 million more passengers a year. Together with the other projects, it brings the total to 120 million.
Other changes at Suvarnabhumi
- The duty-free area will be reworked to add item collection services in arrivals. This will reduce the number of shops.
- A VIP premium service is due to launch this month (November 2026) for businesspeople, celebrities and customers with special needs.
- A fast-track immigration lane is also being introduced.
Don Mueang
AOT is preparing to submit a development plan for Don Mueang to the cabinet. The budget for phase 3 rises from 36 billion baht (set in fiscal 2022) to 69 billion baht. Phase 3 is expected to raise annual capacity to 40 million passengers.
Funding
AOT says the plans are designed to meet growing demand while minimising new borrowing, which reduces the burden on public funds.
Information sourced from Bangkok Post.